Delays, Substitutions and Claims during COVID-19 – Bulletin #9

COVID-19 SPECIAL BULLETIN #9

MATTERS DESERVING IMMEDIATE ATTENTION
Delays, Substitutions and Personal Injury Claims

The consequences of COVID-19 to the architectural, construction and insurance sectors have been deeply
felt, and will continue to be felt – and discussed – into the foreseeable future. The same three matters that
were at top of the list when the COVID-19 protocols were first announced remain equally important and
deserve continuing attention from architects:

Delays and Delay Claims | Substitutions to Your Design | Personal Injury Claims

This Bulletin updates and reinforces the valuable advice presented in COVID-19 Special Bulletin 2, issued
March 24, 2020, which provided a comprehensive discussion of essential risk management practices for the
duration of the pandemic. This Bulletin confirms that the guidance contained in Bulletin 2 is as reliable today
as it was then.

Then, as now, it is more essential than ever that architectural practices maintain careful records of all
instructions and actions. If you aren’t in the habit of doing this already,
start now.

Under the current conditions, with work-from-home protocols and closed borders, it can be difficult to adhere to normal schedules for a number of reasons. These have included: unavailability of some common building materials; slowdowns in professional services; shortages of labour; delays in getting approvals from clients, building departments and consultants; reduced shipping capabilities; and an increase in general indecision and confusion.

It remains clear that any measures implemented to combat the spread of the COVID-19 virus will have continued to have a significant impact on the construction industry, including architects and their consultants.

What Can Architects Do to Manage these Risks?

We cannot stress enough the importance of
record-keeping. Document everything!
Oral agreements will not be helpful to architects when they are faced with seemingly unfounded accusations related to architectural services provided.

Architects may face claims related to several aspects of their practices. The most obvious risk management activity that every architect should observe is the
adherence to the directives of all levels of government
and the “social distancing” protocols being mandated
to halt the spread of the virus. These directives tend to evolve rapidly, and many require changes to the way that architects and their consultants provide their services. It is not “business as usual” for anyone, including architects.

There are many types of potential claims for damages arising from the COVID-19 crisis – and the measures required to combat its spread – that demand proactive
risk management practices.

The measures taken to combat the spread of the virus
will almost certainly involve other outcomes, such as:

• delays in the delivery of architects’ and consultants’
design services;
• delays in the approvals processes applicable to
building projects;
• delays in the production and supply of specified
materials and components;
• shortages and delay in delivery of commonly used
construction materials;
• delay in the construction process and completion
of projects under construction.

Reasons for the delays will continue to include:
• shortages of labour and disruptions to all types of
businesses and organizations due to self-isolation
or illness;
• lack of access to building permit departments or
personnel due to closures of public services
mandated by provincial or municipal authorities;
• inefficiencies arising from clients, authorities, architects
and consultants adapting to “work from home” regimes
– voluntary or mandated by health authorities;
• reduction in production capacity – globally and locally;
• reduction in shipping capability – from abroad and
within Canada;
• uncertainty and confusion.

A predictable outcome of these circumstances will be losses suffered by the owners and any number of entities involved in the design and construction process. Unfortunately, despite the unprecedented circumstances, it is certain that some will attempt to mitigate their losses by pursuing claims against architects and their consultants. Some of these claims may relate to the very measures the architect or others took to aid in the battle against the COVID-19

A predictable outcome of these circumstances will be losses suffered by owners, contractors and any number of entities involved in the design and construction process. Unfortunately, despite the unprecedented circumstances, it is already apparent that some will attempt to mitigate their losses by pursuing claims against architects and their consultants. Some of these claims may relate to the very measures taken by the architect or others to aid in the battle against the virus.

Pro-Demnity will be on hand to vigorously defend Ontario architects who are faced with such claims – as we already do for any other claims against architects.

However, architects can adopt or reinforce risk management approaches that may make them less attractive targets and strengthen Pro-Demnity’s ability to provide a defence.

As mentioned above, there are three areas in particular that will continue to benefit from proactive risk management efforts by architects: Delays and Delay Claims, claims arising from Substitutions to Your Design, and Personal Injury Claims.

1. Delays and Delay Claims

Among the more common challenges faced by architects and the Pro-Demnity Claims team are Delay Claims that result from an allegation by a client, contractor or other party in the chain that error, negligence or failure to act promptly, committed by the architect or one of its subconsultants is responsible for a delay in the progress of the work, and that this delay has caused damages to the other party.

Architects can help themselves counter any such claims throughout this crisis by ensuring they maintain the normal and expected procedures and standards that apply to the provision of architectural services.

Maintenance of comprehensive records of communications with clients, consultants, contractors, subcontractors and suppliers is always good practice.

Of particular importance in defending any Delay Claim is the careful written documentation of any circumstances that arise on a project that may, in turn, trigger or contribute to a delay in any part of the design and construction process. The unprecedented circumstances related to the COVID-19 virus provide added impetus for maintaining comprehensive records. These should include documentation of the array of measures taken by your practice and others in the design, approvals and construction-chain delivery that are related to the COVID-19 crisis.

Many contractors, long before the arrival of COVID-19, had already developed tools for assigning blame for delays to a variety of actions or alleged failures to act, on the part of others upon whom they rely for information. Architects and other consultants are a common target. These efforts to develop a delay claim are sometimes supported by special consultants retained by the contractor to assist in maintaining records and supplying other information for the purposes of developing the claim against an architect, or others.

Faced with the increased opportunities for delays to arise “due to circumstances beyond the control of the contractor” – or any other party that has suffered losses due to the COVID-19 crisis – it may prove doubly important to your defence that you have maintained good records of your communications within the consultant team, your client, your contractors and suppliers, throughout the project.

Design and construction projects extend over considerable periods of time and involve large investments. Failure to meet schedules and investment objectives, for whatever reason, can result in costly losses for clients, contractors and others. Although we are all caught up in common efforts to contain and combat the COVID-19 virus today, there is a very real potential for serious financial losses to be incurred by the measures to contain the virus.

It will not be a surprise if, a year or two from now, today’s common fight against the virus may be overlooked by some of the clients, contractors or others who are currently sharing our experiences. When that happens, your records may be essential to remind everyone that the COVID-19 crisis had an impact on the project that resulted in specific outcomes.

2. Substitutions to Your Design

A major initial concern – that measures taken to combat COVID-19 virus would result in an inability or delay in obtaining specified products and systems – appears to have been less drastic than anticipated, since the province allowed cross-border deliveries to continue without major delays. Nevertheless, architects and consultants may still be presented with substitutions and delay requests, including some that are not actually due to COVID-related causes. All such requests should be carefully documented and evaluated, as to whether “emergency conditions” apply. In these current unprecedented circumstances, architects must maintain their professional standards and duty of care in considering the appropriateness of any substitution.

The current circumstances do not justify any architect’s actions in ignoring the impact of proposed substitutions, or in overlooking those that may happen on the project without its knowledge or express agreement. The Architects Act and Regulations have not been suspended; building codes have not changed; and the standard of care applicable to an architect’s services, advice and approvals has not been reduced. Thus the “special” circumstances related to the COVID-19 virus are unlikely to provide an effective defence to the architect where a substitution fails to perform adequately in the completed project.

Quoting from Pro-Demnity’s December 31, 2016 Bulletin: Dealing with Substitutions to Your Design:

One way or another, the architect will find itself facing allegations of negligence in the provision of its services related to the substitution, including:

failure by the architect to provide a suitable design in the first place; and / or
• acceptance or approval of an unsuitable substitution by the architect; and / or

• failure of the architect to recognize that what was being constructed did not conform to the architect’s design and specifications

Actions or failures to act by the architect may result in the architect being deemed to have accepted or approved of the substitution, thus converting the substitution into the architect’s design, regardless of other considerations.

In addition, failure to advise your client of the consequences that may arise where the substitution was incorporated without professional input may constitute professional misconduct.

Regulation 27 under the Architects Act includes as a prescribed Standard of Practice Item 49.8:

Every member or holder shall present clearly to the member’s or holder’s employer or client the consequences that may be expected from any deviation in a design for which the member or holder is responsible in a case where the member or holder’s judgment was overruled by a non-technical authority.

Apart from the usual considerations respecting any substitution cited in the Pro-Demnity Bulletin there may be a reasonable expectation for the architect and any other design consultants to give “special” consideration to a proposed substitution that may not ordinarily be their first choice or usual practice. The scheduling and other challenges flowing from the restrictions imposed to try to contain the COVID-19 virus may have placed a somewhat different duty of care on architects in these circumstances than what they have been used to or might otherwise have applied.

Nevertheless, the architect’s obligation to adequately investigate and advise its client on the consequences, pro and con, respecting the proposed substitution remains unchanged.

Regardless of the inevitable pressures to do so, be very wary of allowing COVID-19 considerations to justify a decrease in vigilance or diligence respecting substitutions to your and your consultants’ designs.

It is critically important to maintain comprehensive records of all communications regarding the circumstances giving rise to the consideration of any substitutions, whether or not they are related to the COVID protocols. We urge you to observe this risk management practice in your own interests.

3. Personal injury Claims

Personal injury claims against architects are a growing challenge, and COVID-19 creates a whole new source of exposure to such claims. As professionals and business operators, architects are obliged to observe all required or recommended measures to help prevent the spread of the virus. To do otherwise may result in exposure to claims that their negligence has caused, either directly, or indirectly by contributing to the spread of the virus to others – work colleagues, consultants, clients, contractors, tradesmen and others – who may become ill or die.

Even though architects are not responsible for the provision and maintenance of construction job site health and safety measures, as with other personal injury lawsuits, the architect could be blamed for any shortcomings at a construction site resulting in the perceived dangerous condition that causes a personal injury, assuming oversights or lapses were noticed and not brought to the attention of the contractor or owner.

Personal injury claims often involve extremely large sums, and can involve an array of issues, such as: loss of income (short term or lifetime), pain and suffering, long term care and support costs, loss of physical capability or loss of enjoyment of a normal life.

Fortunately, ample advice is available from public health and other knowledgeable authorities. Architects are advised to adopt such advice in their practices, to help manage the risk that their actions or inactions may lead to a claim related to personal injury to others. These measures include, but aren’t limited to:

• avoiding face-to-face meetings – with anyone;
• wearing a mask and observing social distancing, when in-person meetings are unavoidable;
• assurance that their own offices and personnel and the construction sites they visit are employing mandatory and recommended preventive measures;
• in rare instances where physical documents must change hands, making reasonable efforts to assure the materials are “virus-free.”

Architects are encouraged to make it their business to adopt any and all measures available to protect themselves, their colleagues, those they interact with in the course of provision of their services and the community at large, in order to reduce the risk that they may face such a claim.

THINGS YOU CAN DO NOW:

Just as in March 2020, the following practices should be faithfully observed:

  1. Follow all provincial, federal and public health guidance on protective and precautionary measures
    related to COVID-19.
  2. Keep careful and detailed records of actions and instructions related to active projects.
  3. Be vigilant and diligent respecting substitutions arising from fall-out from COVID-19.
  4. Manage client expectations with respect to potential delays due to material or labour shortages,
    and mandated shut-downs.
  5. Utilize the tools and advice respecting COVID-19 provided by the OAA.
  6. Maintain good communications with clients, consultants, contractors and authorities, all of whom
    may be facing restrictions in efforts to address COVID-19

The contents of this Bulletin are provided for general information purposes only. The information contained herein is not legal advice and should not be relied upon as such. Readers must consult their own lawyer respecting the applicability to any particular circumstances of any of the information provided in this Bulletin. Pro-Demnity makes no representation or warranty regarding the contents of this bulletin and does now warrant or guarantee that information in this document, however used, will lead to any particular outcome or result. Pro-Demnity will not be liable for any loss, damage, costs or expense arising by reason of any person using or relying upon information in this Bulletin. in the event of a claim against an architect, the terms and conditions of the pro-Demnity insurance policy will apply. Coverage decisions can only be made at the time a claim arises, based on the allegations and the then known circumstances.

Share this page
Back to top